Sunday, February 22, 2009

02.06 | vertical rebar? uh-oh...

weather-wise, it was a gorgeous day. we all had a full afternoon of icf stacking, rebar cutting, and zip tying. about 5:00, Robert had the revelation that we needed to be putting vertical rebar every 2-3 ft below all of the window openings. Robert wanted to push to get it done today, so time for a system--Robert measured and marked all the walls with the appropriate 2-3 ft intervals, i measured the heights underneath each window and tallied the # of pieces of rebar we needed for each length, Marianne cut all the rebar, and several of the crew got busy installing. whew! done. just in time for the weekend.

No comments:

Post a Comment