02.06 | vertical rebar? uh-oh...
weather-wise, it was a gorgeous day. we all had a full afternoon of icf stacking, rebar cutting, and zip tying. about 5:00, Robert had the revelation that we needed to be putting vertical rebar every 2-3 ft below all of the window openings. Robert wanted to push to get it done today, so time for a system--Robert measured and marked all the walls with the appropriate 2-3 ft intervals, i measured the heights underneath each window and tallied the # of pieces of rebar we needed for each length, Marianne cut all the rebar, and several of the crew got busy installing. whew! done. just in time for the weekend.